**Urgent** [Flow] - upgrade to v0.48.0

Scheduled Maintenance Report for Blockdaemon

Completed

The scheduled maintenance has been completed.
Posted Apr 21, 2026 - 16:30 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 21, 2026 - 16:00 UTC

Scheduled

Blockdaemon will update Flow mainnet nodes to v0.48.0 on 04/21/26. We are updating our nodes due to a release from the Flow foundation. This update applies to all Blockdaemon Flow mainnet nodes, there will be planned downtime of up to 5 minutes per node.

We have tested the release and do not anticipate any unexpected downtime other than mentioned above as a result of the update. If you have any questions or concerns please reach out to your Customer Success Manager.
Posted Apr 21, 2026 - 13:44 UTC
This scheduled maintenance affected: Blockdaemon Validators (Flow Consensus, Flow Verification) and Protocols (Dedicated Nodes) (Flow).